Perfect World

Superfund / Washington

NPL Site · EPA Region 10

Oeser Co

Bellingham, Whatcom County, Washington

Industry (inferred)Wood & Paper
Wood preserving & treating
EPA IDWAD008957243
HRS score69.34
ProposedDecember 23, 1996
ListedSeptember 25, 1997
Construction completeSeptember 20, 2011
Deleted

Regulatory timeline

  1. December 23, 1996Proposed for the NPL
  2. September 25, 1997Established on the NPL (final listing)
  3. September 20, 2011Construction completed

Projected reinspection cycle

CERCLA requires a five-year review while hazards remain on site. These dates are projected from this site's cleanup timeline — they are estimates, not EPA-published dates. Check the site progress profile for the actual review schedule.

  1. September 20, 2021Projected five-year review (reinspection), cycle 2
  2. September 20, 2026Projected five-year review (reinspection), cycle 3
  3. September 20, 2031Projected five-year review (reinspection), cycle 4

Official EPA records