Perfect World

Superfund / Florida

NPL Site · EPA Region 4

Harris Corp. (Palm Bay Plant)

Palm Bay, Brevard County, Florida

Industry (inferred)Uncategorized
EPA IDFLD000602334
HRS score35.57
ProposedApril 10, 1985
ListedJuly 22, 1987
Construction completeJuly 1, 1998
Deleted

Regulatory timeline

  1. April 10, 1985Proposed for the NPL
  2. July 22, 1987Established on the NPL (final listing)
  3. July 1, 1998Construction completed

Projected reinspection cycle

CERCLA requires a five-year review while hazards remain on site. These dates are projected from this site's cleanup timeline — they are estimates, not EPA-published dates. Check the site progress profile for the actual review schedule.

  1. July 1, 2023Projected five-year review (reinspection), cycle 5
  2. July 1, 2028Projected five-year review (reinspection), cycle 6
  3. July 1, 2033Projected five-year review (reinspection), cycle 7

Official EPA records