NPL Site · EPA Region 4

Zellwood Ground Water Contamination

Zellwood, Orange County, Florida

Industry (inferred)Groundwater & Area-wide
Groundwater plume
EPA IDFLD049985302
HRS score51.91
ProposedDecember 30, 1982
ListedSeptember 8, 1983
Construction completeSeptember 16, 2003
Deleted

Regulatory timeline

  1. December 30, 1982Proposed for the NPL
  2. September 8, 1983Established on the NPL (final listing)
  3. September 16, 2003Construction completed

Projected reinspection cycle

CERCLA requires a five-year review while hazards remain on site. These dates are projected from this site's cleanup timeline — they are estimates, not EPA-published dates. Check the site progress profile for the actual review schedule.

  1. September 16, 2023Projected five-year review (reinspection), cycle 4
  2. September 16, 2028Projected five-year review (reinspection), cycle 5
  3. September 16, 2033Projected five-year review (reinspection), cycle 6