Superfund / Mississippi
Industry (inferred)Chemical Manufacturing
Pesticides & agricultural chemicals
EPA IDMSD008182081
HRS score31.36
ProposedMarch 18, 2022
ListedDecember 22, 2022
Construction complete—
Deleted—
Regulatory timeline
- March 18, 2022Proposed for the NPL
- December 22, 2022Established on the NPL (final listing)
Projected reinspection cycle
CERCLA requires a five-year review while hazards remain on site. These dates are projected from this site's cleanup timeline — they are estimates, not EPA-published dates. Check the site progress profile for the actual review schedule.
- December 22, 2027Projected five-year review (reinspection), cycle 1
- December 22, 2032Projected five-year review (reinspection), cycle 2