Perfect World

Superfund / North Carolina

NPL Site · EPA Region 4

FCX, Inc. (Washington Plant)

Washington, Beaufort County, North Carolina

Industry (inferred)Uncategorized
EPA IDNCD981475932
HRS score40.39
ProposedJune 24, 1988
ListedMarch 31, 1989
Construction completeSeptember 22, 2005
Deleted

Regulatory timeline

  1. June 24, 1988Proposed for the NPL
  2. March 31, 1989Established on the NPL (final listing)
  3. September 22, 2005Construction completed

Projected reinspection cycle

CERCLA requires a five-year review while hazards remain on site. These dates are projected from this site's cleanup timeline — they are estimates, not EPA-published dates. Check the site progress profile for the actual review schedule.

  1. September 22, 2025Projected five-year review (reinspection), cycle 4
  2. September 22, 2030Projected five-year review (reinspection), cycle 5
  3. September 22, 2035Projected five-year review (reinspection), cycle 6

Official EPA records