Perfect World

Superfund / Michigan

NPL Site · EPA Region 5

Roto-Finish Co., Inc.

Kalamazoo, Kalamazoo County, Michigan

Industry (inferred)Uncategorized
EPA IDMID005340088
HRS score40.70
ProposedOctober 15, 1984
ListedJune 10, 1986
Construction completeMarch 31, 1997
Deleted

Regulatory timeline

  1. October 15, 1984Proposed for the NPL
  2. June 10, 1986Established on the NPL (final listing)
  3. March 31, 1997Construction completed

Projected reinspection cycle

CERCLA requires a five-year review while hazards remain on site. These dates are projected from this site's cleanup timeline — they are estimates, not EPA-published dates. Check the site progress profile for the actual review schedule.

  1. March 31, 2022Projected five-year review (reinspection), cycle 5
  2. March 31, 2027Projected five-year review (reinspection), cycle 6
  3. March 31, 2032Projected five-year review (reinspection), cycle 7

Official EPA records