Perfect World

Superfund / Missouri

NPL Site · EPA Region 7

Newton County Wells

Joplin, Newton County, Missouri

Industry (inferred)Uncategorized
EPA IDMOD985798339
HRS score50.00
ProposedJanuary 19, 1999
ListedJuly 27, 2000
Construction completeApril 13, 2009
Deleted

Regulatory timeline

  1. January 19, 1999Proposed for the NPL
  2. July 27, 2000Established on the NPL (final listing)
  3. April 13, 2009Construction completed

Projected reinspection cycle

CERCLA requires a five-year review while hazards remain on site. These dates are projected from this site's cleanup timeline — they are estimates, not EPA-published dates. Check the site progress profile for the actual review schedule.

  1. April 13, 2024Projected five-year review (reinspection), cycle 3
  2. April 13, 2029Projected five-year review (reinspection), cycle 4
  3. April 13, 2034Projected five-year review (reinspection), cycle 5

Official EPA records