Town SquareParks & Rec WatchFebruary 20, 2020
Parks & Rec Advisory Board · February 20, 2020

"Just putting another band aid" — tennis and pickleball push back on the GO Bond court plan

The first presentation of the GO Bond sports court rehabilitation to the board drew sustained objection from tennis and pickleball players, who said earlier meetings had led them to expect full resurfacing and professional-grade courts rather than crack repair. The board tabled the action to a special meeting and asked for two revisions — one with as much professional grade as possible, one showing what the existing money buys. A parent also told the board a discrimination complaint he filed in December 2018 was still unresolved.

Called to order 6:05 p.m. · adjourned 8:23 p.m. · 14 pages · source document ↗

If you read nothing else

  • The board tabled action on the GO Bond sports court rehabilitation to a special meeting, asking for two revisions: one including as much professional-grade work as possible, and one showing what would be done with the money already available.
  • The consultant put the whole construction budget on the record: "There is only $1.5 million to do the construction for all the projects."
  • Loretta Reyes of the Las Cruces Tennis Players Association said cracks were repaired and courts restriped five, six, seven years ago and are coming apart now and unsafe: "to repair cracks is just putting another band aid."
  • Samuel Ramos told the board a complaint he filed with the director in December 2018 over the removal of his daughter from a coach-pitch team had still not been fixed, and that the January 2020 copy of the league agreement was identical to the one he reviewed on September 1, 2019.
  • The board approved the Public Art Master Plan to go to City Council, and approved a special meeting for March 9, 2020 on the East Mesa Recreational Complex and the dog park. The record shows no meeting held March through May.

Who was in the room

4 of 7 seats represented.

Present

  • Robert Harrison — Chair
  • Eli Guzman
  • Cassie McClure
  • Stan Engle

Absent

  • Megan Schuller
  • Maryln Zahler
  • Eric Montgomery

Staff

  • Sonya Delgado — CLC Parks and Recreation
  • Franco Granillo — CLC Parks and Recreation
  • Cathy Mathews — CLC Parks and Recreation
  • Robert Nunez — CLC Parks and Recreation
  • Wilfred Martinez — CLC Parks and Recreation
  • Hazel Nevarez — CLC Parks and Recreation
  • David Maestas — CLC Public Works
  • Tony Trevino — CLC Public Works
  • Sreedevi Bhathala Mohanraj — CLC Public Works
  • Ceci Vasconcellos — CLC Community Engagement
  • Lorenzo Zepeda — Quality of Life, Public Art
  • James Woods — CLC KLCB

Others

  • Paul Dugie — Souder Miller & Associates
  • Joseph Fuemmeler — Desert Peaks Architecture
  • Ruben Contreras — Desert Peaks Architecture
  • Miguel Cheng-Guajardo — ECM International, Inc.
  • Arturo Gonzalez — ECM International, Inc.
  • Mike Heard — Highland Enterprise
  • Mark Hettinga — Highland Enterprise
  • Gregory Shervanick — Resident
  • Alexis Ruiz — FC Grande
  • Gerry & Kathy Rittenberry — Citizen
  • Rich & Dorothy Robinson — Citizen
  • Loretta M. Reyes — Las Cruces Tennis Players Association
  • Anniz Barva — Las Cruces Tennis Players Association
  • Ed Carnathan — Visit Las Cruces
  • Rebecca Courtney — City Art Board

Public comment

Kept at length on purpose. Every point raised is listed, in the order the minutes record it.

Samuel Ramos5. Public Participation
  • He filed a complaint in December 2018 with Parks and Recreation Director Sonya Delgado because the Las Cruces Youth Baseball Association (LCYBA) failed to address a discrimination issue that took place against his daughter.
  • His daughter had played two years of t-ball, moved up to coach pitch baseball, and was removed from that team by the coaches.
  • He filed a complaint with LCYBA and they did not address it.
  • LCYBA later said they have no jurisdiction as to what teams do between the end of summer baseball and the beginning of fall ball.
  • With that noted by the league, and Delgado knowing about it, Delgado said she had a new agreement that would solve the loophole under which LCYBA had no jurisdiction over what happened to players or what coaches can do.
  • On September 1, 2019 he came to a meeting where the agreement was going to be given to the board; Delgado tabled that discussion stating she needed to conduct more research.
  • In January 2020 he received another copy of the agreement — the same copy he received on September 1, 2019, with no changes made after his review.
  • Since no changes were made, he asked Delgado how she was going to fix the loophole, and noted it could also be a discrimination issue against a boy with a disability, where a team can get rid of a boy with a disability.
  • Delgado said that once the agreement comes back from legal she would address it with the league.
  • He said his issue is that if LCYBA did not address the issue two years ago with him or with her, why leave it up to the league to address an issue she can fix via the agreement.
  • He said the loophole is very clear, Delgado knows what the loophole is, and LCYBA stated what the loophole is — the no-jurisdiction clause.
  • He said Parks and Recreation and Delgado need to step up and fix the loophole so it does not happen again in the future.
  • He said it has been a year and a half and who knows if it has happened to another little girl or a boy with a disability.
  • He thanked the board for their time.
It's been a year and a half and who knows if it has happened to another little girl or a boy with a disability.
On the record in response

As recorded within the comment itself: Delgado said once the agreement comes back from legal, she would address it with the league. No board discussion of the complaint is recorded, and the minutes record no response to Ramos after he finished.

Kathy Rittenberry7.1 GO Bond Projects / Sports Courts
  • After the bond passed, at an initial meeting, the proposal was that Apodaca and Frenger would be changed to pickleball courts.
  • When the tennis courts and pickleball courts were being divided up at that time, the reason Young stayed as a tennis court park was that Frenger was in the picture — so now, why would Young not be for pickleball.
  • She asked why it would not be better to use Young Park as pickleball, and said Young Park was not discussed at the time because Frenger was in the picture.
  • She said it looks like a tennis court is being left at Apodaca; she was advised that is what is there now.
  • She said what they were told at the last meeting was that when the court was resurfaced it would be resurfaced as a sports court, not painted with grit on it, and that the surface would be a sports court surface recommended by the USTA.
  • She asked that the information on the surface be sent to her, and was told the USTA manual would be sent.
  • She asked whether the design team and architects have done other pickleball court facilities.
  • Later, she asked how many basketball courts are in the City, and whether they are in the schools too.
  • She said tonight's presentation is different than what was proposed before, and that is the problem.
  • When Guzman said organizations should be brought to the board meeting, she said that if he is asking to see these people at board meetings, he should let her know.
On the record in response

Maestas said Frenger was never included in the verbiage for the GO Bond, so it would have to be done separately from this project. Delgado said Frenger was discussed as a possibility for pickleball if there was enough money, but right now there is not; she said Parks and Recreation was approached by a group wanting to hold a basketball tournament at a facility with an outdoor basketball court and to redo that court, and if that happens, Frenger can be added back online in place of one of the basketball courts. Delgado said Young Park was never discussed in the initial conversation as being pickleball and, because it was not in the initial conversation, it cannot be added. Maestas said they are going off the breakdown provided as part of the GO Bond packet before it was voted on and need to stick to that because that is what the citizens of Las Cruces voted and approved. Granillo said 18 to 20 basketball courts are maintained throughout the City, spread through different parks and not in a facility. Maestas said there are basketball and tennis courts in schools but the City has no jurisdiction and they are not open for public use. Maestas said it will not be a concrete surface with paint on it.

Loretta M. Reyes — Las Cruces Tennis Players Association7.1 GO Bond Projects / Sports Courts
  • She expressed the association's concern over converting any other tennis courts to pickleball courts, considering there will be new pickleball courts at the East Mesa Complex.
  • She said this was decided and discussed early in the process with the two groups together.
  • She wanted to make sure they maintain the twelve courts at Lions and the two courts at Young, for the purpose of having their leagues.
  • For Lions, the listed work is repair cracks and restripe; she asked whether there would be any resurfacing, because they were led to believe there would be complete resurfacing.
  • She said there are dead spots and areas where the water sits.
  • She said five, six, seven years ago cracks were repaired and courts were restriped, but they are coming apart now and are unsafe.
  • She said she does not think repairing a crack is going to do it, and her concern is that if another band aid is put on, how long is it going to last — it is not the proper way to deal with what is out there.
  • She said she understands budget, but asked about priority among the projects: the tennis community has waited a long time to have a nice facility, and she does not understand the priority.
  • She asked whether there are plans to further address the birds on the light covers, and whether that would be taken care of before the courts are done or whether heavy machinery would be brought onto the courts afterward.
  • She asked whether the information on how far the budget will go will be brought back to the public.
  • She said it is important to know when design and construction happen in advance, as it affects their tournaments and there are USTA rules.
  • She said the last meeting she recalls attending was at the library, and that this is the first time presenting to a board that has some decision-making authority; she is hearing for the first time that only cracks will be filled in, and that the board is being asked to move forward. She said that for her, this is disappointing.
to repair cracks is just putting another band aid
They were led to believe the courts would be resurfaced.
On the record in response

The minutes record "Not sure who responded, but response was" the original estimate for these GO Bond projects — the four projects in question — was split up equally among the projects, and that based on the earlier estimates they need to see how to adequately improve all these courts. Maestas said her point being raised is what helps with prioritization, that this is the initial proposal and not the final one, and that there is an opportunity now to look at it based on comments received and on the fact that there may be other money from other places. On bringing the budget answer back, Maestas said the intention is that if comments are very different from the design, to give people the information back as to what modifications can or cannot be made; whether that is done in a meeting depends on how simple it is — if the response is just "yes, it will be resurfaced instead of cracks," an email notification would be sent. On scheduling, the recorded response is that the schedule can be provided and obtained from Delgado. The question about the birds on the light covers is not recorded as answered.

Briana Ramos7.1 GO Bond Projects / Sports Courts
  • She asked whether the pond at Young Park will be refilled with water. Delgado said the pond was filled over the summer.
Mr. Ramos7.1 GO Bond Projects / Sports Courts
  • He said he does not mean to offend anybody and that he comes from a community of soccer, baseball, and softball.
  • He said the discussion in families is what pickleball is, how it helps the youth in Las Cruces, and whether it is traditionally an adult sport or a youth sport.
  • He said the City needs to gravitate to the youth instead of youth not having facilities to go to and use, so they do not gravitate to the other side — crime and juvenile delinquency.
  • He asked how it can help the youth in the City.
  • He said Meerscheidt Recreation Center is the only indoor facility for the City's children.
  • He said this is just a comment: look at how facilities are going to help the community with the youth, a place to go.
  • He said even having tournaments — basketball and soccer — brings revenue into the City.
  • He said the City does not have big soccer tournaments and does not have basketball tournaments because it does not have the facilities yet.
  • He said a lot of local organizations go out of town for these tournaments and provide those communities with Las Cruces money.
On the record in response

Maestas said the voters agreed with Ramos, so part of the bond in place is for the East Mesa Recreation Complex to have soccer fields and multiuse fields, and baseball fields will also be put in as part of the project. He said there have been some public meetings and there will be more.

Anniz Barva — tennis player, previous Las Cruces Tennis Players Association board member7.1 GO Bond Projects / Sports Courts
  • She said she is involved in youth tennis programs and they have a series of things coming up.
  • She asked for a general ballpark idea of when the repair and repainting of Lions Park might happen, so they have a general idea for future planning.
On the record in response

Maestas asked her to turn her schedule in to Delgado so the work can be planned around her schedule. No date was given.

Gerry Rittenberry7.1 GO Bond Projects / Sports Courts
  • He said this is the sixth or seventh meeting on these issues and there were other meetings, so he wonders how this is new news to the board.
  • He said pickleball and tennis were talked about along the stream, notes are taken, and he wonders who reads those notes.
  • He referred to different meetings that were held at which votes were taken, and said his curiosity is who talks to whom.
On the record in response

Guzman clarified that the board meets every month and the organizations are not present to discuss these issues. Maestas clarified there are two different meetings — the ones being referred to are specific to the East Mesa Recreation Complex and similar items, not the Parks and Recreation Advisory Board meeting — and that this is the first time staff was ready to come to the board with the project, now that they have the magnitude of the projects and the interested groups. Chair Harrison said the previous meetings were specific to all of the GO Bond and tonight is specific to courts.

Rich Robinson7.1 GO Bond Projects / Sports Courts
  • He said there was a consultant from El Paso at one of the meetings who said these courts were going to be professional grade courts.
  • He said he was not quite finished with his comment, and told the board that if they want to see the support for pickleball in this retirement community, they should hold the next meeting in a gym.
  • He said there is a huge pickleball community in this town and in the state.
  • He referred back to the consultant from El Paso.
On the record in response

The minutes record a "Mr. Sedillo" saying there appears to be confusion about the different meetings being held, that when professional courts were discussed it was for the East Mesa Recreation Sports Complex — and note "There was an immediate disagreement response." Sedillo said the previous meetings were for informational input from the public, that the project is called a sports court rehabilitation, that after input was gathered the design team went to the courts to see what could be fixed and adjusted to make them playable, and that it was never agreed in the meetings what kind of surfacing or construction would be used. Arturo Gonzalez spoke up saying he was the consultant from El Paso: in tonight's presentation the fences are moving out and surface is being added; the main issue raised in the meeting being referred to was that those courts were too small, recreational size, and the next step is what they call professional, which means adding two more feet. He said at East Mesa two courts will be championship size and the others will be pro, that the budget is very tight, and that there is only $1.5 million to do the construction for all the projects.

7.1 GO Bond Projects / Sports Courts — David Maestas and Tony Trevino, Public Works

$1.5 million
Total construction budget, all court projects
Stated by Arturo Gonzalez
August 2018
GO Bond approved by voters
8
Pickleball courts at Apodaca
Delgado's clarification; a member of the public was told sixteen earlier in the same discussion
12 at Lions, 2 at Young
Tennis courts to be maintained
As asked for by the Las Cruces Tennis Players Association
18 to 20
City-maintained basketball courts
Granillo; spread through different parks, not in a facility
Split equally among the four projects
Original GO Bond estimate
Speaker not identified in the minutes

Maestas said what was being presented is a result of the GO Bond project voted on by voters in August 2018 — a preliminary idea of what is going to take place with the parks and sports courts — and that staff would then ask the board for approval to move forward with what was presented, after input and comments received at this meeting.

Maestas introduced the team: Tony Trevino, Engineer and Architect Program Manager overseeing all of the GO Bond projects; Sreedevi Mohanraj, City Architect; ECM International, Inc., hired as Program Manager to oversee each of the GO Bond projects, represented by Arturo Gonzalez and Miguel Cheng-Guajardo; Paul Dugie of Souder Miller & Associates on the design portion; and Mark Hettinga of Highland Enterprise, the contractor handling the construction (design build) part.

Trevino began the presentation with background on the GO Bond and what progressed to the present.

Dugie presented site by site. Hillrise Basketball Court: the court is in good condition; the proposal is to repair the cracks (milling and filling, or remove and replace — the crack goes all the way through and there is a big differential), sand it all down smooth, and restripe.

Metro Verde: the park has a ponding problem; the proposal is to remove the existing surface, add some height and drainage to stop water ponding on the court, put sport surfacing back down, and restripe.

Four Hills area: the basketball court is in good condition but has a ponding problem; the proposal is to repair cracks, remove and replace an area where the concrete is crumbling, and restripe.

Apodaca Park: on the northwest side there is a playground out in the sun all the time, and the proposal is to put shade over that area. For the pickleball courts, the proposal is to increase the size of the court by adding concrete onto the sides to allow the creation of eight pickleball courts, remove and relocate fence, remove and relocate a light post, repair cracks, resurface and restripe.

Benavidez Community Center basketball court: all cracks were measured; the recommendation is total removal and replacement with a five- to six-inch slab with reinforcing rebar inside if funding is available — if not, repair cracks as best as possible and restripe.

Lions Park: repair cracks, repaint to match existing, and restripe.

El Cardon basketball court: the recommendation is to remove and replace, but if there are no funds, repair cracks and restripe.

Klein Park basketball court: a lot of cracks, so the recommendation is to remove and replace; if not, repair and restripe.

Young Park: the proposal is to remove and replace the big group shelter and replace as many of the single shelters as possible, removing the concrete slab so it starts from the ground up with a good structure. For the tennis courts, remove the existing surface, repair the cracks, resurface, and restripe.

Frank O'Brien Papen Community Center: the basketball court has a little cracking but looks like it has other problems; the recommendation is to remove and replace if funds are available, and if not, repair cracks and restripe.

Trevino said that, as Dugie said, a lot of these courts will be repair or total reconstruction based on funding, and the amount of sport cushion for all the projects will be determined by the budget across all the projects.

Arturo Gonzalez said an idea had just surfaced: on surfacing for tennis and pickleball there is ultimate surfacing, which is cushioned, professional surfacing, which is less cushion, and paint with grip. He asked what would be preferred — four courts with good surfacing, or eight courts with less surfacing. The minutes record no answer.

Maestas said one thing that can be done, and the reason for these meetings, is to get input from the crowd, for two reasons: for the construction, Klein and Young will be pushed back toward the end of construction if possible, so if Delgado can get Klein taken care of through other funding sources it would allow the opportunity to put in something different; and a couple of years from now there is another opportunity for another bonding cycle, meaning the City can go back to the voters.

Maestas said pickleball courts are also going in at the East Mesa Recreation Complex as part of this GO Bond.

McClure asked if the board would review modifications; Chair Harrison said, or the board can table.

Chair Harrison said he does not think his question was answered — whether the projects were listed in priority order or just listed straight through. The minutes record "Don't know who spoke, but response was" that all that was received in the request for proposal was a list of projects, and that they have not heard any priorities.

Chair Harrison said the two groups present that night are the most heartfelt and need to be listened to in the aspect of funding, and asked whether basketball groups were at previous public meetings. Maestas said the listing of projects and locations was part of the GO Bond package, and that this is the first meeting on these courts, so the participation seen at this meeting is where the priority is.

Engle clarified that in this case it seems basketball would get almost no priority, considering public input was heavily stacked toward tennis and pickleball.

Engle asked whether action is being requested so the City can begin to prioritize and start the work, or whether staff will come back to the board with priorities needing action. Maestas deferred back to the board, if the board wants staff to come back with options based on input received.

Delgado said the Parks and Recreation Advisory Board members know when there are meetings and cannot come to all of them; when something comes to this board it comes as information for them to absorb and then comes back for action. Her suggestion was to take the information received that night back to the program manager for review and then bring it back to the board with specific information addressing the tennis and pickleball concerns, and for action.

After McClure's motion, Maestas asked whether it could be tabled to a special meeting, with the date dependent on review of the two specific situations. McClure amended her motion accordingly.

Engle said the board is not going to magically have more money the next time it meets, and that he understands a priority is not known yet and the board is just being informed of a general priority. Sedillo's recorded response was that they will come back and define what will be removed to accommodate some things. Engle clarified that if this is tabled there would be a more specific outline of how to proceed with the rehabilitation; Maestas said there will be a specific outline addressing the concerns brought forward, and that there will be an opportunity to know the status of Klein being paid for, which would allow additional funding.

8.2 GO Bond Project / Hadley Complex — Tony Trevino, Public Works (Informational)

Trevino said the Hadley Sports Courts Complex (Hadley, Maag, Hardy and Paz) is also to be rehabilitated as part of the GO Bond project, design build.

Joseph Fuemmeler of Desert Peaks Architecture introduced himself and Ruben Contreras, project manager, as part of the design build team along with Highland Enterprises as prime. He said this is the first public meeting, that it would cover site conditions and ask about priorities from the public, that lighting has been received from the City as the major priority with everything else falling under that as a possible, and that the first thing is to decide on cost and get input from the public.

Contreras reported conditions at Maag: dugouts with water damage to sheeting, structure showing signs of rust, missing covers on some receptacles; foul ball protection is chicken wire with holes in some locations and rusted; spectator shade in good condition; restroom facilities well maintained but with accessibility issues; concession facilities a bit dated and cramped, non-accessible, needing floor drains, with a dated point of sale; exterior conditions fair to poor, wood siding starting to show cracks in the paint with signs of rot, stucco failing in various locations, water soaking up into wall, and some drainage issues.

Jim Hardy: dugout fencing with minimal rusting; some wood sheeting exhibits water damage; structure shows rusting; foul ball protection is non-existent; shade structure has variation in fabric color, fabric fair to good with some small holes and minimal rusting. Facilities are the worst of all complexes: bathrooms well maintained but with issues to exhaust fans and door hardware starting to fall off; there is room to make the bathrooms accessible except for the women's restroom, which would require quite a bit of rearranging. Concession facilities are the worst of all the ball fields — corrosion in the structure, water infiltration from the ceiling caused by the evaporative cooler with a lot of calcium deposits dripping to the floor, limited space, point of sale boarded up and unusable. Exterior: staining water on the top floor causing rust on the sealed deck, paint on the ceiling block chipping and not bonding well, stucco failing in various locations, dated light fixtures.

Paz: fairly good condition. Some rusting in the dugout steel structure, very minimal on the fence; chicken wire foul ball protection appearing to rust; spectator shade with a few rips and some water pooling; structure could use paint touchup for rusting; one bent pole. Restroom facilities need to comply with accessibility standards, missing an exhaust fan, some openings in the ceiling. Concession facilities had some failures in finishes — holes in the ceiling, limited space, minor discoloration in the paint. Exterior has a few instances of stucco failure around the corners and some penetrations within the stucco; trim around the openings is a bit dated and could be replaced.

Ron Galla T-Ball: dugout steel structure exhibiting rust in some locations; chain link fence post with some rust around the wells; spectator shading good to fair with some small holes; steel structure could use paint touchups; restroom facilities could use a few minor adjustments to make them accessible.

In summary: Maag is in fair condition but concessions are inadequate and restrooms have minor accessibility issues, with exterior conditions not good; Jim Hardy would take extensive work to make restrooms accessible and its concessions were in poor condition; Paz needs some minor exterior improvements, its restrooms need to comply with accessibility standards, its concessions were in fairly good condition, and its spectator shade has only a few areas needing improvement; at Ron Galla the restroom facilities are well maintained and the spectator shade could use some improvement.

Maestas emphasized that lighting is the biggest thing for all four complexes, which will take a big chunk of the money, and that the improvements to those lights will be substantial.

Chair Harrison asked if there would be any architectural design to see what this will look like in the future. Trevino said the next step is to do a feasibility study.

6. Old Business — 6.1 Overview Work Session and 6.2 Future Board Meeting Dates, Times and Locations

Both items, tabled from January 16 to this meeting, appear in the document as headings with no discussion recorded beneath them. They were tabled again by motion, to the March 19 board meeting.

7.2 Public Art Master Plan — Lorenzo Zepeda, Quality of Life Department

CIP 2%
Proposed public art funding
Still needs to go to Ordinance

Zepeda presented the Public Art Master Plan as it would affect Parks and Recreation, saying there is a considerable amount of overlap between what the new program intends to do and what Parks has been doing. He provided the board a handout, the Standard Commissioning Process Chart.

He said there is an extensive collection of current City-owned public art pieces installed in park locations that were completely maintained by Parks and Recreation. With the establishment of Las Cruces Public Art and the Master Plan going toward resolution, he came to share the plan with the board.

He said most of the initiatives will be driven by the City Art Board, whose goal is to commission art, and that the program should function by taking the space that needs art into account and creating something that integrates with that space.

He said the main thing about the Public Art Program is that it will no longer be required to be maintained by Parks and Recreation. After the Resolution for the Master Plan they will go to Ordinance, and when that happens they will have their own budget to maintain existing artworks as well as upcoming artwork. The relationship with Parks and Recreation will continue because their goal is to put art on public property, which happens to be in parks most of the time; the extent of the relationship will be vetting projects through Parks to make sure everything recommended is viable, with funding coming from Las Cruces Public Art.

Engle clarified that the Parks and Recreation Advisory Board's role would be only if a public art piece would be going on park property. The response was yes.

Chair Harrison asked if any of the art projects were on the GO Bonds going through. Delgado said the art projects with regard to the GO Bond are for buildings — the new animal shelter, the new aquatics facility. Zepeda said on funding they are looking at a Capital Improvement Program (CIP) 2%, but it still needs to go to Ordinance, and they are also hoping that includes all vertical structures in addition to public safety impact fees and park impact fees.

Zepeda said a huge goal of the program is placemaking — creating a visual identity for the City of Las Cruces and making it more visually easy to navigate, including opportunities for landmark pieces. They also want to find opportunities through community collaboration and partnerships, consider educating in the arts and creating community engagement art projects, help make these programs longer standing and more established, create opportunities for local artists to have work, and, as the last component of the Master Plan, professionalize the local pool of artists.

McClure asked how the selection committee would be picked. Zepeda said selection is an ad hoc group separate from the Art Board; depending on the project they want to include an owner, a user, and an Art Board member, so the committee would be made up of the actual stakeholders. They also hope to add some public input sessions.

Zepeda introduced Rebecca Courtney, Vice Chair of the City Art Board. Chair Harrison asked if this had already been approved by the Art Board. Courtney said it had, and was taken to council, who made several recommendations about art selection committees and about the Art Board itself, wanting to make sure a diverse population was included. She said wording was changed in the category of City Art Board duties and art selection committees to address Council's concerns.

7.3 Special Meeting / East Mesa Recreational Complex (March 9) — Sonya Delgado

Delgado asked the board to hold a special meeting on the East Mesa Recreational Complex and the dog park so the board could view concepts. She said it would be informational, not for action.

She said there will also be a public input meeting March 17, and that when the concept is refined it will come back to the board for action in April.

8.1 Keep Las Cruces Beautiful (KLCB) — James Woods

over 4,000
Volunteers
over 53 tons
Trash collected
1,100
Third-grade presentations
over 400
Graffiti locations abated
5th consecutive year
Presidents Circle Award
7 of about 30 New Mexico affiliates received it

Woods received, for the fifth consecutive year, the Presidents Circle Award. There are about 30 affiliates in the State of New Mexico and only seven programs throughout the state received the award.

Across all the cleanup groups — Team Up to Clean Up, Great American Clean Up, Toss No Mas, Adopt a Spot, youth cleanups, and other community service cleanups — they have over 4,000 volunteers and have collected over 53 tons of trash, from boots on the ground and roll-off containers.

Education: 1,100 presentations to third graders, educating on recycling, litter, graffiti and illegal dumping; activities with over 400 students in the City's After School Program educating them about the environment.

The graffiti crew abated over 400 locations, from dumpsters to light poles to walls.

Upcoming 2020 events: March 21, Team Up To Clean Up, District 6; April 11, Great American Clean Up; April 16, Water Festival; April 18, Earth Day Recycle Reuse Fashion Show; April 25, Volunteer Fair.

9. Staff member comments

$5 per coffee bag sold
Beck's Coffee sponsorship
To A. Fielder Memorial Safe Haven youth program

Catanach invited the board to the Chaos Collaboration Art Show February 21 and 22, 2020 at the Frank O'Brien Papen Community Center, and said Saturday, February 29, 2020 is the first Father Daughter dance at the same center.

Nunez said the spring semester is in full swing with the Out of School Time program, that staff will meet with Las Cruces Public Schools the first week of March to solidify sites for summer programs, and that things are going very well with Youth Services.

Granillo said the Parks section is wrapping up its winter projects list, that the IPM Ad Hoc committee has met twice now and is going very well with communications open, and that they should have a good IPM document in June to present to City Council.

Mathews reported on two projects: play equipment for Benavidez Community Center now has a contract on board, with a preconstruction conference beginning in March and construction starting mid-March, and new play equipment expected end of March or beginning of April; and Metro Verde on Saracco Road near the intersection with Sonoma Ranch Blvd., where a brand new park with the working title The Tower Park has reached substantial completion, has gone through punch list, and has a couple more items to address before the park opens to the public.

Delgado said that on the Klein Park basketball court, a gentleman has come forward who wants to hold a tournament there and is working with a sponsor to redo the entire basketball court — tear it all apart and put down a brand new regulation court, including new goals. If this happens, dollars will shift to another project in the GO Bond. He wants to hold the tournament in August.

Delgado said the City has an agreement with Beck's Coffee. Nunez said a sponsorship was created with Beck's Coffee and the youth programs: students from the youth programs created the artwork and were involved with the writeup regarding A. Fielder Memorial Safe Haven, which will get $5 from every coffee bag sold to go toward the youth program.

Delgado said two monuments are coming into Veteran's Park, the Gold Star Memorial and the Wall of Honor. The Wall of Honor is first and the Gold Star Memorial will be in May. A vendor will take care of the slab for the Wall of Honor and park staff will do the one for the Gold Star Memorial.

Delgado said there is a Unidad Park GO Bond meeting February 22, 10 a.m. to noon at Unidad Park. Parks and Recreation emailed all program participants, it was put in the newspaper, and there is signage at the park. She said this will be the first input meeting for that park, there will be a couple of other meetings, and as it gets close to rollout it will come through this board. McClure added it is on social media and said the phrasing was good.

Delgado recapped that she talked to the Public Works team and staff is going to take the lead to set up a meeting with the pickleball players and the tennis players — a mini charrette with them.

Delgado said league agreements are still with Legal. She had emailed the board that there is language in the Fees & Charges saying the board will have authority over the leagues, and that this will be going to Council soon.

Nevarez asked the board that when she sends the agenda for the board meeting, they please notify her at that time whether they will attend, so she knows if there will be a quorum.

10. Board member comments

McClure asked if there is any way to put seating — a bench — at Meerscheidt in the back hallway where the practice rooms are. Delgado said she will check on this.

Recorded votes

3. Approval of AgendaNo discussion, motion carried unanimously.
Move action item 7.1 to come after Public Participation, and discussion item 8.2 to follow the moved item 7.1.
Moved by Stan Engle · seconded by Cassie McClure
4. Approval of MinutesMotion carried unanimously.
Approve the minutes of January 16, 2020 as presented.
Moved by Cassie McClure · seconded by Eli Guzman
7.1 GO Bond Projects / Sports CourtsSuperseded by the amended motion below; no separate vote is recorded on this version.
Table the action of the sports courts until the next meeting to see two different revisions that include as much as possible with professional grade options, and one to see what would be done with the money that we have.
Moved by Cassie McClure · seconded by Eli Guzman
7.1 GO Bond Projects / Sports Courts (amended)Motion carried unanimously.
Table the action of the sports courts to a special meeting, with date and time publicized to the public and those present, to see two different revisions that include as much as possible with professional grade options, and one to see what would be done with the money that we have.
Moved by Cassie McClure · seconded by Eli Guzman
Amended at Maestas's request, who asked whether it could be tabled to a special meeting with a date to follow once the two revisions were reviewed.
6.1 / 6.2 Old BusinessMotion carried unanimously.
Table the Parks and Recreation Overview Work Session and Future Board Meeting Dates, Times and Locations to the March 19 board meeting.
Moved by Cassie McClure · seconded by Stan Engle
7.2 Public Art Master PlanMotion carried unanimously.
Approve the Public Art Master Plan to go to City Council.
Moved by Cassie McClure · seconded by Stan Engle
7.3 Special Meeting / East Mesa Recreational ComplexMotion carried unanimously.
Approve the special meeting for March 9, 2020.
Moved by Cassie McClure · seconded by Stan Engle
11. AdjournmentMotion carried unanimously. Chair Harrison adjourned the meeting at 8:23 p.m.
Adjourn the meeting.
Moved by Cassie McClure · seconded by Stan Engle

Left open at the gavel

David Maestas / Public Works
Two costed revisions of the sports court plan, to a special meeting
The board's tabling motion requires staff to return with two revisions — one including as much professional grade as possible, one showing what would be done with the money on hand — at a special meeting whose date and time are to be publicized to the public and to those present. No date was set at the gavel.
Sonya Delgado
LCYBA league agreement loophole
Samuel Ramos's December 2018 complaint remains unresolved. The agreement is with Legal; Delgado said that once it comes back she would address it with the league. Ramos said the January 2020 copy was identical to the September 1, 2019 copy after his review. The board took no action and the minutes record no board discussion of the complaint.
Sonya Delgado
League agreements at Legal, and board authority over leagues
Delgado said league agreements are still with Legal, that language in the Fees & Charges gives the board authority over the leagues, and that this will be going to Council soon. No date given.
Staff
USTA surfacing manual to Kathy Rittenberry
Rittenberry asked that information on the court surface be sent to her and was told the USTA manual would be sent. No confirmation or date recorded.
David Maestas
Whether the budget answer comes back to the public
Reyes asked whether the information on how far the budget will go will be brought back to the public. Maestas said the intention is to give information back on what modifications can be made, and that whether it is done in a meeting depends on how simple it is — a simple answer would go out as an email notification.
Sonya Delgado
Design and construction schedule for the tennis groups
Reyes said knowing the schedule in advance matters because it affects tournaments governed by USTA rules. The recorded response was that the schedule can be provided and obtained from Delgado. Barva asked for a ballpark date for Lions Park repair and repainting and was asked to submit her own schedule to Delgado instead.
Unassigned
Birds on the light covers at the tennis courts
Reyes asked whether there are plans to further address the birds on the light covers, and whether that would be handled before the courts are done or after with heavy machinery on the courts. The minutes record no answer.
Unassigned
Four courts with good surfacing, or eight with less
Arturo Gonzalez put the tradeoff to the room — ultimate (cushioned), professional (less cushion), or paint with grip — and asked which was preferred. The minutes record no answer from the board or the public.
Unassigned
Whether the project list was in priority order
Chair Harrison said he did not think his question was answered. The minutes record an unattributed response that all that was received in the request for proposal was a list of projects, and that no priorities had been heard.
Sonya DelgadoBefore the August tournament
Klein Park tournament funding and the GO Bond dollars it would free
A sponsor may fund a complete rebuild of the Klein Park basketball court for an August tournament. If it happens, dollars shift to another GO Bond project and Frenger could be added back for pickleball. Maestas said there will be an opportunity to know the status of Klein being paid for, which would allow additional funding.
Sonya Delgado
Mini charrette with pickleball and tennis players
Delgado said she talked to the Public Works team and that staff is going to take the lead to set up a meeting with the pickleball and tennis players. No date set.
BoardMarch 19, 2020
Overview work session and future meeting dates, times and locations
Tabled from January 16 to this meeting, and tabled again to the March 19 board meeting with no discussion recorded. The record contains no March 2020 meeting.
Sonya DelgadoMarch 9, 2020
Special meeting on East Mesa Recreational Complex and the dog park
Approved for March 9, 2020, informational only, with a public input meeting March 17 and the refined concept returning to the board for action in April. The record contains no March or April 2020 meeting.
Tony Trevino
Hadley complex feasibility study
Chair Harrison asked whether there would be architectural design showing what the complexes will look like. Trevino said the next step is to do a feasibility study. No date given.
Franco Granillo / Sonya DelgadoJune 2020
Citywide IPM document to City Council
Granillo said the IPM Ad Hoc committee has met twice and that they should have a good IPM document in June to present to City Council — the same June deadline Delgado gave the board in January.
Sonya Delgado
Bench seating at Meerscheidt
McClure asked whether seating could be placed in the back hallway where the practice rooms are. Delgado said she will check on this.
Board
Attendance confirmations for quorum
Nevarez asked board members to tell her whether they will attend when she sends the agenda, so she knows whether there will be a quorum. Three of seven members were absent from this meeting.