Parks & Rec Advisory Board · December 11, 2025

Ten projects in one sitting, and a gazebo whose lights nobody will claim

With no action items on the agenda, the board heard fall and winter athletics numbers from Meerscheidt and a staff walk-through of ten capital projects, from Apodaca Park's aquatic playground to a three-acre park proposed on the west side of Villa Mora Dam. Public comment concerned missing lights at the Pioneer Women's Park gazebo.

Called to order approximately 6:00 p.m. · adjourned Not recorded — the adjournment entry on page 5 is unreadable · 5 pages · source document ↗

If you read nothing else

  • No action items. Two discussion items and staff comments filled the meeting.
  • Ten capital projects were run through in one block: Apodaca, Benavidez, East Mesa (bike park and complex), Chandler Tank, Doña Ana Move Trail, La Llorona, Pioneer Women's, Veterans Memorial and Villa Mora Dam.
  • Meerscheidt's 2026 slate is finalized: 23 programs and leagues plus three new youth camps — 26 programs out of one rec center.
  • The Pioneer Women's Park gazebo is rebuilt in steel, but four interior lights near it are gone and its outlets are off at the breaker after vandalism. A neighbor was told the city did not put up the Christmas lights.
  • Bingham said that as long as Veterans Memorial Park is a park, it needs to be allowed to be a park — after veterans said soccer and a playground were inappropriate there.
  • The record does not show an adjournment motion; the entry is unreadable.

Who was in the room

5 of 7 seats represented.

Present

  • Jeremy Williams — At large member
  • Laura Haas — District 6 (Chair)
  • Charles Beard — District 2
  • Alana Bradley — District 4
  • Aracely Tellez — District 3

Absent

  • Miley Sarah Grandjean — District 1
  • Kylie Aleja Jenkins — District 5

Staff

  • Steven Bingham — Director, Parks & Recreation
  • Franco Granillo — Deputy Director, Parks & Recreation
  • Catherine Mathews — Landscape Architect, Parks & Recreation
  • Jake Gutierrez — Aquatics Administrator, Parks & Recreation
  • Zach Hernandez — Recreation Facility Manager, Meerscheidt, Parks & Recreation

Others

  • George Pearson — public

Public comment

Kept at length on purpose. Every point raised is listed, in the order the minutes record it.

George Pearson6. Public Participation
  • Asked about the gazebo at Pioneer Women's Park.
  • Said the project seems to be completed but there is some confusion or interest on the lights.
  • Said there have been a lot of complaints about the lighting in the park.
  • Said that is because there were four interior lights near the gazebo and those are now gone.
  • Said that for the past several years the city has been decorating the gazebo with Christmas lights.
  • Said someone in the neighborhood called and the city said they did not do that.
  • Said he would like to know more about this.
On the record in response

No direct response is recorded at the public participation item. Later, under 8.2 Project Updates, Cathy Mathews said the gazebo project is completed with the wooden structure replaced by a steel structure, the current phase adds pergolas back per the original gazebo, people can make reservations online for use of the gazebo and can ask for the lighting and staff will program the lighting, and the electrical outlets are turned off at the circuit breaker because they were vandalized. The record does not connect that to the four missing interior lights or to the Christmas lights question.

8.1 Fall sports program

138
Flag football participants
434 participants
Youth basketball
six divisions
64 teams / 512 participants
Adult sand volleyball
met capacity, as every year
52 teams / average 416 participants
Adult indoor volleyball (2026)
four divisions
23
2026 programs and leagues
plus three new youth camps
26
Total programs at Meerscheidt
January 3
Facility calendar runs through
6
Grass volleyball courts
for adults
1-2
Volunteers per baseball team
sometimes 3-4

Zach Hernandez presented athletics for fall and winter 2025. Completed youth leagues: flag football with 138 participants, and youth basketball with six divisions and 434 participants. Adult sand volleyball finished at capacity, as it does every year — 64 teams and 512 participants. The Spooky Spikes Volleyball Tournament and the Holiday Hits Volleyball Tournament were also named.

Daily programming ran August through November. A new facility calendar now runs through January 3rd. It includes adult volleyball Monday, Wednesday and Friday; adult pickleball daily with a single session on Saturdays; adaptive sports for volleyball and basketball on Tuesdays and Thursdays; corn hole; Zumba Gold tailored to senior women Monday and Wednesday; and Dancercise for a slightly younger crowd Tuesday and Thursday.

For 2026, adult indoor volleyball is taking place now with four divisions, 52 teams and an average of 416 participants. Youth indoor soccer is registering.

All 2026 programs have been finalized — 23 programs and leagues, plus three new youth camps to be offered, so 26 programs run just out of Meerscheidt Rec Center.

Grass volleyball has taken off; staff can set up six courts for adults. They did the first-ever dance camp for young ladies aged 6-10. Teen nights and Friday-night sand volleyball are running. Some programs are also held at Provencio and Notre Dame. Youth soccer is offered at six and under, eight and under, and 10 and under. There is room for expansion if needed.

Jake Gutierrez said a balance for recreation programs is that there are other options within the city, so there is lots of variety. One issue is not enough volunteers; the department does some wonderful things for volunteers including a luncheon and goodie bags. Baseball runs one to two volunteers per team, sometimes three to four.

Franco Granillo said End Zone has used and reserved the fields and pays a fee, and also uses the schools. The goal is always how best to serve the community; End Zone is for profit so things are a bit different. Several organizations do rent sports spaces.

8.2 Project updates — the funded work

350 acres
East Mesa BLM lease
part of it to become a bike park
1:1
Benavidez LWCF match
matched with park impact fees

Apodaca Park: staff are developing an aquatic playground and a multiuse path, with a grant from the Land and Water Conservation Fund to execute a portion of the master plan. The existing restroom will be used to put in a splash pad — staff call it an aquatic playground because it will be more than just a splash pad. The work also includes a trail around the entire park, addressing parking, and a plaza near the pickleball courts, with more amenities at the pickleball courts because they are quite popular.

Benavidez Community Center Park: also supported by a Land and Water Conservation Fund grant, matched one-to-one, with the match coming from park impact fees. Staff will update the practice area — it is not large enough to be a full baseball or softball field — bringing in turf grass, trails, and added trees.

East Mesa Public Recreation Complex bike park: the intention is to take part of the 350 acres leased from BLM and build a bike park, so mountain bikers will have a place to go.

Chandler Tank Park: a stormwater management area and facility, to which staff are bringing neighborhood park amenities — a playground, picnic shelters, some grass, and a bit of parking.

Doña Ana Move Trail: supported by a lot of funding sources, including capital outlay funding and a grant from the Paso del Norte Foundation. Staff are partnering with Elephant Butte Irrigation District to underground a portion of the EBID Las Cruces Lateral from University to College to Union, and from Union all the way to Main Street, with the trail built over the top.

8.2 Project updates — under construction and proposed

3 acres
Villa Mora Dam park
west side of the dam; phased as funding is limited
not currently funded
East Mesa signage

East Mesa Public Recreation Complex: Phase 1 is constructed. Phase 2 is under construction — the sports complex and recreation complex, plus a parking lot. A skate park is already completed in the southern end. Under construction are a playground, a restroom, and basketball courts, with sand volleyball courts eventually. Signage is very expensive and not currently funded; staff said that as the site is under construction, signage at this time is not appropriate.

La Llorona Park: supported by General Obligation Bond money. The restroom is being replaced and upgraded, the existing playground space maximized, the parking lot resurfaced and restriped, and trails have been upgraded and made accessible. Drinking fountains, signage and wayfinding signage are included.

Pioneer Women's Park: the gazebo project is completed, with the wooden structure replaced by a steel structure. The current phase is adding pergolas back per the original gazebo. People can make reservations online to use the gazebo and can ask for the lighting, which staff will program. The electrical outlets are turned off at the circuit breaker because they were vandalized.

Veterans Memorial Park: has some recent and ongoing improvement. The extended parking area was completed last year. Staff are upgrading the restroom and extending the memorial walkway so people can more easily get around the park and into the disc golf area and the area behind the dam with trails. The playground is in the master plan to be returned.

Villa Mora Dam Project: at Triviz and Madrid. On the west side of the dam staff propose to build a three-acre park, ensuring pathways will not interfere with any running water. It will be phased as funding is limited, and would include a trail system, a turf grassed area, a picnic plaza with shade structure, and a small playground.

A question was raised about the La Llorona trail and some cracks in the trail. The city is aware of the issues outside of the park boundaries, but it is not part of the current project.

9. Staff member comments

184
Staff wellness participants
city employees
February 7
Youth indoor soccer league begins
December 22 - January 2
Winter break programming
7:30 to 5:30
Saturday the 13th, 8:00-12:00
Dumpster day
five roll-off locations

Jake Gutierrez said he is filling in for Robert Nunez. Keep Las Cruces Beautiful neighborhood dumpster day will be Saturday the 13th, 8:00 to 12:00, with roll-off locations at Young Park, East Mesa Recreation Center off of Porter, Henry Benavidez Community Center, Mesilla Park, and Frank O'Brien.

Out-of-school-time winter break programming runs December 22nd through January 2nd, 7:30 to 5:30, at Jornada Elementary and East Mesa Recreation Center off of Porter.

The Youth Development and Diversion Program will partner with CYFD, Doña Ana County, and the communities of Las Cruces, Hatch, Sunland Park, Anthony and Chaparral, offering developmental, social and educational community-engaging programs and activities to strengthen youth and family relationships.

On athletics: adult indoor volleyball is in week two; youth indoor soccer registration is ongoing and will reopen for a few more spots, with the league beginning February 7th. On December 26th the facility will be open from 1:00 to 5:00 p.m.

The wellness area for city staff has multiple programs going on, with 184 employees participating.

Aquatics: on December 26th the aquatic center and natatorium will be open 7:30 a.m. to 12:00 p.m., and the gym at the aquatic center will be open until 3:00 p.m. On a question about being closed during the lunch hour, staff said data has been tracked from 12:00 to 4:00, there have to be a certain amount of staff on board, staffing is the issue, and their staffing is largely from the university.

Zach Hernandez said they are wrapping up the season for maintenance, removing the final cedar posts that were deteriorating, and sending staff to recertify. Tree lighting was held this past weekend. He reported that Karen Woods, former VAB chairperson, wants to install a wind phone in Veterans Park — an old-fashioned phone mounted on a square tube installed in a planter area or within the park, giving a veteran the opportunity to make the phone call and have a conversation.

Steve Bingham wished everyone a Merry Christmas and good holidays. He reported that veterans felt playing soccer and a playground were inappropriate at Veterans Memorial Park. His position, as recorded, is that if they want to make it a memorial and not a park the city is open for that, but the park funds used in building the park would have to be repaid so that a park could be built in the area — and as long as it is a park, it needs to be allowed to be a park.

10. Board member comments

2
Closed sessions on the skate park

Board Member Charles Beard said he missed the opportunity with the skateboard park issues. He reported that City Council has had two closed sessions to discuss progress and resolution, and that the city is still pursuing completion of the skate park.

11. Next meeting date

The next meeting was set for January 15, 2026.

Recorded votes

4. Approval of the AgendaMotion passed unanimously
Approve the Parks and Recreation Advisory Board Meeting Agenda for December 11, 2025.
Moved by Alana Bradley · seconded by Charles Beard
5. Approval of the MinutesMotion passed unanimously
Approve the Parks and Recreation Advisory Board Meeting Minutes of October 16, 2025.
Moved by Aracely Tellez · seconded by Charles Beard
No corrections are recorded.
12. AdjournmentNot recorded
Not recorded.
Moved by · seconded by
Item 12 appears on page 5 but the text beneath it is unreadable in the scan — no mover, no seconder, no outcome and no time. The signature line below it reads only "Chair ers/".

Left open at the gavel

Unassigned
Pioneer Women's Park gazebo lighting
George Pearson asked why four interior lights near the gazebo are gone, and why a neighbor was told the city did not put up the Christmas lights it has hung for the past several years. Staff's project update described reservable programmable lighting and outlets shut off at the breaker after vandalism, but did not answer either question.
Unassigned
Cracks in the La Llorona trail
Raised in discussion. The city is aware of issues outside the park boundaries, but they are not part of the current project. No remedy or timeline recorded.
Staff
East Mesa Public Recreation Complex signage
Signage is very expensive and not currently funded. Staff said signage is not appropriate while the site is under construction. No funding source or date recorded.
Steven Bingham
Veterans Memorial Park — memorial or park
Veterans said soccer and a playground are inappropriate at the park. Bingham said the city is open to making it a memorial rather than a park, but the park funds used to build it would have to be repaid. No decision or process recorded.
Unassigned
Wind phone at Veterans Park
Karen Woods, former VAB chairperson, wants to install a wind phone in Veterans Park. No approval, siting decision or staff response is recorded.
Jake Gutierrez
Aquatic center lunch-hour closure
A question was raised about closing during the lunch hour. Staff said data has been tracked from 12:00 to 4:00, a certain amount of staff must be on board, staffing is the issue, and staffing is largely from the university. No change or report-back was promised.
Unassigned
Not enough volunteers
Gutierrez named volunteer shortage as an issue for recreation programs. No recruitment plan or follow-up recorded.
City
Walnut/skate park completion
Beard reported two City Council closed sessions on progress and resolution, and that the city is still pursuing completion of the skate park. No completion date recorded.
Staff
Villa Mora Dam park phasing
The proposed three-acre park will be phased because funding is limited. No phase schedule or funding source recorded.
Staff
Veterans Memorial Park playground
The playground is in the master plan to be returned. No date recorded, and it sits against the veterans' objection to a playground at that park.